YAMAL LNG Project
Period: June 2015-August 2017
Owner: Total & Novatec & CNPC
EPC Contractor: Technip & JGC & CHIYODAModule Contractor: PJOE Jutal(Penglai)、COOEC(QD)
Scope: hot & cold insulation for equipment and pipe line, engineering, procurement, installation, Temp-162℃~ +500℃,pipeline 277000elm, equipment 32000㎡。
Material Supply: total 49 categories, including cellular glass, rock wool, fiberglass, acoustic sheet, adhesive, sealant, stainless steel accessories etc.
Manpower: peak period 1500 labors, accumulative manhour 5,5 million